import uuid
from datetime import date
from types import SimpleNamespace
import pytest
from app.scheduling_service import calculate_schedule, check_for_cycle
def test_cycle_detection():
id_a = uuid.uuid4()
id_b = uuid.uuid4()
id_c = uuid.uuid4()
edges = [
(id_a, id_b),
(id_b, id_c),
]
# Adding C -> A should detect cycle
assert check_for_cycle(edges, id_c, id_a) is True
# Adding A -> A (self-loop) should detect cycle
assert check_for_cycle(edges, id_a, id_a) is True
# Adding C -> D (new node) should not detect cycle
id_d = uuid.uuid4()
assert check_for_cycle(edges, id_c, id_d) is False
def test_cpm_forward_and_backward_pass():
id_a = uuid.uuid4()
id_b = uuid.uuid4()
id_c = uuid.uuid4()
t_a = SimpleNamespace(id=id_a, duration=3, planned_start=date(2026, 1, 1), parent_id=None, progress=0)
t_b = SimpleNamespace(id=id_b, duration=4, planned_start=None, parent_id=None, progress=0)
t_c = SimpleNamespace(id=id_c, duration=2, planned_start=None, parent_id=None, progress=0)
# A (3d) -[FS + 1 lag]-> B (4d) -[FS + 0 lag]-> C (2d)
rel_ab = SimpleNamespace(from_task_id=id_a, to_task_id=id_b, relation_type="FS", lag_days=1)
rel_bc = SimpleNamespace(from_task_id=id_b, to_task_id=id_c, relation_type="FS", lag_days=0)
res = calculate_schedule([t_a, t_b, t_c], [rel_ab, rel_bc], project_start=date(2026, 1, 1))
sched = res["tasks_schedule"]
# Task A: 2026-01-01, duration 3 is a gap -> ends 2026-01-04
assert sched[id_a]["planned_start"] == date(2026, 1, 1)
assert sched[id_a]["planned_end"] == date(2026, 1, 4)
# Task B starts right after A finishes (Jan 4) plus 1 lag day = Jan 5
assert sched[id_b]["planned_start"] == date(2026, 1, 5)
# B: duration 4 gap -> Jan 5 + 4 = Jan 9
assert sched[id_b]["planned_end"] == date(2026, 1, 9)
# Task C starts Jan 9, duration 2 gap -> ends Jan 11
assert sched[id_c]["planned_start"] == date(2026, 1, 9)
assert sched[id_c]["planned_end"] == date(2026, 1, 11)
# All three are on critical path
assert id_a in res["critical_path"]
assert id_b in res["critical_path"]
assert id_c in res["critical_path"]